Construction rises above ground level: 1st floor structure completed
18. 3. 2026

Construction rises above ground level: 1st floor structure completed

Section A: safer access to underground levels

In Section A, prefabricated staircase flights are being installed in the underground levels. This step improves access to individual floors while enhancing safety on site.

Section B: foundation slabs in progress

The construction of foundation slabs is gradually progressing across Section B. Work is currently focused on part B2, where reinforcement is being installed as a key phase prior to concrete pouring.

Sections A1 and A2: vertical structures completed

In Sections A1 and A2, vertical structures (walls and columns) on the 1st floor level have been completed. Preparations are now underway for formwork of the slab above this level, marking another significant step in the building’s vertical growth.