In Section A, concrete walls for the 2nd above-ground floor are currently being completed.
Section B is focused on ceilings and walls of the 1st underground floor, while works are gradually beginning to transition into the above-ground levels as well.
A significant milestone has also been reached in Section C1, where a drilling rig for piling operations has recently arrived. Due to the future ramp location, access to this area had previously been limited.
Work has also started on the underground infiltration pits, which will form part of the project’s technical infrastructure. At the moment, excavation and earthworks are underway.
In the coming days, technical installations in the garages will begin as well, including sewage systems, water distribution, electrical installations and ventilation systems.
With each new phase, the future shape of the new urban district is becoming increasingly visible.