Construction works are in full progress (video)
16. 2. 2026

Construction works are in full progress (video)

In Section A, concreting and reinforcement of the basement floor slabs are currently underway. On the lower levels, the gradual removal of slab formwork is in progress. In part of Section A, formwork and reinforcement works are also ongoing for the 5.2-metre-high walls of the first above-ground floor.

In Section B, reinforcement of the foundation slabs is underway, while in Section C, preparations for the building’s foundation works are in progress.

At the same time, backfilling around the completed parts of the structure is being carried out progressively.